Progress of Ciliwung River Dredging Work in Kebon Melati Touches 80 Percent

The dredging work on Ciliwung River West Flood Canal (KBB) on Jalan Tenaga Listrik, Kebon Melati, Tanah Abang, Central Jakarta has reached 80 percent.

We are targeting to complete it this year

Central Jakarta SDA Sub-agency's Maintenance Section Head, Achmad Daeroby stated, dredging has been carried out since March 2011, from Jalan Pintu Air Karet until Jalan K.S. Tubun along 1,047 meters.

"We are targeting to complete it this year," he mentioned, Thursday (3/3).

South Jakarta SDA Optimizes Reservoirs and Rivers Dredging

It was carried out with a depth of 1.5 meters. It was estimated around 55,282 cubic meters of mud would be dredged from the site.

"Every day, we dredge and transport 44,062 cubic meters of mud," he added.

His side deployed 20 personnel and 3 amphibious excavators,  1 long arm excavator, and 10 dump trucks for dredging the Ciliwung River.

"We expect it can increase the river's capacity and can be completed on time," he said.

Linked News
Popular News indeks
  1. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye762 personDessy Suciati
  2. Transjakarta Reaffirms Ban on Busking in Mikrotrans and Bus Stops

    access_time02-10-2026 remove_red_eye551 personAldi Geri Lumban Tobing
  3. 1,500 Runners and Pets Hit the Track for World Rabies Day Run 2026

    access_time03-10-2026 remove_red_eye549 personAnita Karyati
  4. Commission D Supports Reserve Fund for Long-Term Infrastructure

    access_time02-10-2026 remove_red_eye527 personFakhrizal Fakhri
  5. Jakarta Logs 0.13% Inflation as Chicken, Chili, and Rice Push Prices Up

    access_time03-10-2026 remove_red_eye510 personFakhrizal Fakhri