Pengerukan Kali Ciliwung BKB Capai 79,70 Persen
....
photo Anita Karyati - Beritajakarta.id

Progress of Ciliwung River Dredging Work in Kebon Melati Touches 80 Percent

The dredging work on Ciliwung River West Flood Canal (KBB) on Jalan Tenaga Listrik, Kebon Melati, Tanah Abang, Central Jakarta has reached 80 percent.

We are targeting to complete it this year

Central Jakarta SDA Sub-agency's Maintenance Section Head, Achmad Daeroby stated, dredging has been carried out since March 2011, from Jalan Pintu Air Karet until Jalan K.S. Tubun along 1,047 meters.

"We are targeting to complete it this year," he mentioned, Thursday (3/3).

South Jakarta SDA Optimizes Reservoirs and Rivers Dredging

It was carried out with a depth of 1.5 meters. It was estimated around 55,282 cubic meters of mud would be dredged from the site.

"Every day, we dredge and transport 44,062 cubic meters of mud," he added.

His side deployed 20 personnel and 3 amphibious excavators,  1 long arm excavator, and 10 dump trucks for dredging the Ciliwung River.

"We expect it can increase the river's capacity and can be completed on time," he said.

Linked News
Popular News indeks
  1. 1,262 Personnel Ready to Support Bhayangkara Anniversary Cleanliness

    access_time30-06-2025 remove_red_eye584 personAldi Geri Lumban Tobing
  2. 4,072 Damaged Roads in Central Jakarta Have Been Repaired

    access_time04-07-2025 remove_red_eye354 personFolmer
  3. Dishub Pushes Digitization of Parking Management for Local Revenue

    access_time01-07-2025 remove_red_eye298 personFakhrizal Fakhri
  4. Transjabodetabek Bekasi-Galunggung Route Officially Operates

    access_time03-07-2025 remove_red_eye247 personDessy Suciati
  5. Pramono Asks for Onrust Island Tourism Potential to Be Optimized

    access_time04-07-2025 remove_red_eye247 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik