Progress of Ciliwung River Dredging Work in Kebon Melati Touches 80 Percent

The dredging work on Ciliwung River West Flood Canal (KBB) on Jalan Tenaga Listrik, Kebon Melati, Tanah Abang, Central Jakarta has reached 80 percent.

We are targeting to complete it this year

Central Jakarta SDA Sub-agency's Maintenance Section Head, Achmad Daeroby stated, dredging has been carried out since March 2011, from Jalan Pintu Air Karet until Jalan K.S. Tubun along 1,047 meters.

"We are targeting to complete it this year," he mentioned, Thursday (3/3).

South Jakarta SDA Optimizes Reservoirs and Rivers Dredging

It was carried out with a depth of 1.5 meters. It was estimated around 55,282 cubic meters of mud would be dredged from the site.

"Every day, we dredge and transport 44,062 cubic meters of mud," he added.

His side deployed 20 personnel and 3 amphibious excavators,  1 long arm excavator, and 10 dump trucks for dredging the Ciliwung River.

"We expect it can increase the river's capacity and can be completed on time," he said.

Linked News
Popular News indeks
  1. East Jakarta Satpol PP Deployed to Ensure Safe Eid Travel Period

    access_time16-03-2026 remove_red_eye1008 personNurito
  2. Car Free Night Held on Eid Eve, Be There!

    access_time19-03-2026 remove_red_eye697 personDessy Suciati
  3. Pramono Inaugurates 26 Home Renovation Units

    access_time16-03-2026 remove_red_eye663 personDessy Suciati
  4. Homecoming Travelers Surge Seen at Tanjung Priok Terminal

    access_time17-03-2026 remove_red_eye624 personAnita Karyati
  5. Jakarta Leaders Join Residents for Eid al-Fitr Prayer at City Hall

    access_time21-03-2026 remove_red_eye591 personFolmer